Who does what in a validated label system project

In a regulated plant, three parties share the work of putting a label system into use: you, as the regulated company; Numaco, as the integrator; and the vendor of the label software. Most project trouble starts where nobody wrote down which of the three owns a step. This page writes it down.

The split follows GAMP 5, Second Edition. Under GAMP 5 the regulated company always owns the validation, and suppliers contribute documents and testing. So the last column is never ours.

The twelve steps

01

First conversation

You

Describe the labels, the systems that feed them and the deadline

Numaco

Free first engagement: a half-day review of your label print chain, ending in a written list of gaps

02

Inventory of the current label print chain

You

Give access to the label layouts, the printers and the data sources

Numaco

Record every layout, data field, printer and interface in use today

03

User requirements specification (URS)

You

Write and approve it

Numaco

Comment on what the label software can and cannot do

04

Risk assessment

You

Lead it and approve it

Numaco

Contribute what we know of the system's failure modes, such as a wrong template or a lost print job

05

Functional and configuration specification

You

Review and approve

Numaco

Write it: how the system will meet each requirement in the URS

Software vendor

Product documentation

06

Configuration

Numaco

Build the label templates, connect the data source, for example SAP output, and set up the printers

07

Supplier documentation

You

File it

Numaco

Pass it on and explain it

Software vendor

Release notes, quality documents and any validation package for the product

08

Testing before go-live

You

Witness and sign

Numaco

Support your team while it runs the tests on your site

09

Installation and operational qualification (IQ, OQ)

You

Approve the protocols and the results

Numaco

Support your team in drafting and executing the protocols

Software vendor

Test scripts, where the vendor supplies them

10

Performance qualification (PQ)

You

Run it in production, with your products and your people

Numaco

Support on site or remotely

11

Validation report and release

You

Write, approve and release

12

Change control after go-live

You

Raise and approve every change

Numaco

Make the change, test it and document it under your change control

Software vendor

Product updates and their release notes

What follows from the table

Validation is yours. We support your team through it, and we write the specification and the traceability matrix. We cannot approve documents, and we never release a system for GMP use.

What you receive from us

The functional and configuration specification from step 5 and the traceability matrix, signed by us, in English, German or Italian, as PDF and as editable files so your quality unit can bring them into its own templates. The full list is on page 1.4, IQ/OQ/PQ scope.